The holding cost that never shows up in the flip calculator is the one that ends the deal
A hard money loan on a gut project typically prices at one percent a month or close to it, and most people building a flip model factor that in correctly enough. What disappears from the model is the compounding effect when the project slips four months, the lender extends at a penalty rate, the insurance renewal hits on month seven instead of month four, and the property taxes come due on a building that has not sold. Take a property bought at 180k with a 144k loan at 1.1 percent monthly. At month four the carry on the loan alone is about 6,300. If the project slips to month eight, that number is not doubled, it is higher than doubled once you price in the extension fee, which on a standard hard money note often runs one to two points just to get the extra 60 days. Add a six-month insurance premium that the carrier will not prorate on a vacant gut, and a mid-year tax installment on the assessed value before renovation depressed the number, and a project that modeled at 41k profit is sitting at 22k before the agent commission comes out. The mechanism is not that hard money is expensive. The mechanism is that every cost category has its own renewal date, and they almost never align with the resale date. The fix is to build the model around three timelines: the one where the project closes on schedule, the one where it runs 60 days long, and the one where it runs 120 days long, and then ask whether the purchase price still works at the third number. If the answer is no, that is a purchase price problem, not a contingency problem. What timeline did you use when you last underwrote a gut, and did you run a version where the carry stretched past the original loan term?