The scope walk is the only reason this refresh landed near budget
Bought a 1,100 sf three bed in a tired but stable suburb last spring. It's rented now at $1,650 and the rehab finished at $39,400 against a $38,000 budget. Everything I read before this said expect 20 percent over, so 3.7 percent over feels like a win worth writing down.
The one thing I did differently: I paid a contractor $400 to walk the house with me and write the scope himself, room by room, before anybody bid it. He was not bidding the job and he knew that going in. He wrote 41 lines. Then three crews bid the same 41 lines and I could actually compare them, because they were pricing the same words.
Where it landed: kitchen cabinets and counters 14,200 two baths 9,100 LVP through the whole floor 5,600 paint inside 3,400 panel swap plus odds and ends 4,900 rot under the back threshold, found in week two 2,200
What nearly broke it: cabinet lead time went from three weeks to seven after I ordered. The crew had another job starting and if they'd left I would have lost them for a month, which is the story I keep reading in here. My GC resequenced and did both baths and the flooring first, and I swapped to an in-stock door style I liked less. Six and a half weeks instead of five.
What I'd keep: the paid scope walk, and the rule that no change happens until there's a dollar figure in a text message and I answer yes. The 2,200 of rot was the only change order all job and I knew about it the day they opened the wall.