The clock question matters a lot here and the answer is worth getting right in writing, fast.
The statutory language ties the substantial improvement test to the QOF's holding period for the property, which means the period starts when the fund takes title, not when your capital arrives at the fund level. Your closing attorney's answer is consistent with the statute as most practitioners read it. The two people who told you it starts on your investment date may have been conflating your personal 180-day reinvestment window with the fund-level improvement clock. Those are two different clocks running in parallel, and mixing them up is a common source of confusion in this structure.
That said, I am not giving you tax or securities law advice here, and the specific determination for your deal requires your tax counsel to confirm the position in writing against current Treasury regulations and any guidance issued since the 2025 extension. This matters more now because the One Big Beautiful Bill Act changed elements of the program's structure, and you want confirmation the analysis is based on current law, not pre-2025 guidance. Get that written opinion before you do anything with the draw schedule.
The assumption doing the most work in your model is that four months of buffer existed and could be traded against contractor pace. If the fund-acquisition date is correct, you may have less runway than you thought but more than the worst case. Run the draw schedule against the fund-acquisition date as the start point and find out exactly where you land.
The risk you have not named is what happens if the contractor slips further. You are watching pace right now, but have you stress-tested the schedule against a 60-day additional delay and confirmed whether a cure or extension mechanism exists in your fund docs?
What does your QOF operating agreement say about timeline extensions if the improvement test is at risk?