Contractor wants 40 percent up front on a 31,000 cosmetic scope
Helping on the paperwork side of a small flip and the general contractor's proposal asks for 40 percent at signing, 40 percent at what he calls substantial completion, 20 percent at final. The scope is paint, LVP, two vanities, counters, fixtures, exterior cleanup. Nothing custom, nothing with a long lead time except the counters.
12,400 before anyone shows up feels heavy to me for a job with almost no material deposits in it. He says it's how he covers crew mobilization. His references check out and his timeline is six weeks.
The person whose money it is wants to sign tomorrow. I'm the one saying wait. I don't know if I'm being sensible or just inexperienced about how trades actually get paid.