Do you hold a cosmetic scope open for the first week or lock it before closing
I've been building my scope sheets off walkthrough video and photos, and I'm now arguing with myself about when the sheet becomes final. Two approaches I've watched people use.
Lock it at contract. Every line item priced, materials ordered to arrive on day two, contractor paid against a fixed sheet, no changes without written approval and a price. Timeline is the shortest possible and you know your number before you own the house.
Or hold it open for the first five to seven days. You get in, pull carpet, look at what's actually under it, run every faucet, then finalize. You lose a week of carrying cost and your materials arrive later, but you don't order 2,400 of LVP for a floor that turned out to be sound hardwood, and you don't paint a ceiling you're about to open for a leak.
The compression argument cuts both ways for me. Margins are thin enough that a week of holding costs matters, and thin enough that one wrong 2,400 order matters too. Locking early also gives contractors a cleaner bid, which usually means a lower bid. Holding open means the first week's crew is doing demo on an unpriced scope, which is where I've seen hourly work turn into a bad habit.
When does the cosmetic scope become final?