My bathroom tile guy walked off the Wrocław Street triplex mid-demo and I ate $2,100 in sunk labor

Had him in for three weeks, demo done, waterproofing done, backer board up. He found a bigger bathroom job across town, told me Thursday afternoon he'd finish "after that one," which in contractor time means never. I don't have a signed scope with a completion date, just a handshake and a WhatsApp thread, so I have nothing to hold him with. The $2,100 covers his demo days and the backer board install, all paid out already. Now I'm looking at a half-gutted bathroom in unit 2 with the tenant in unit 1 sharing a wall and getting restless. I need someone in there by Monday or I'm eating another week of apologies to the tenant. Every tile guy I've called this week is either six weeks out or wants a 40 percent deposit before they'll even do a site visit, which I'm not doing again without something signed. If anyone in the forum has worked out a contract clause that actually keeps a tile sub from walking mid-job, I want to see the language.

2 replies

The clause that actually worked for me was a mobilization-and-milestone structure, not just a completion date. I split the job into three paid stages, demo complete, substrate ready, tile set and grouted, and the contract says any unpaid milestone gets forfeited if the sub abandons before that stage is signed off by me. The piece nobody mentions until it bites them: add a per-diem liquidated damages line, something like $150/day past the agreed substantial completion date, because without a number attached the "completion date" clause is basically decorative. I did $150/day on a kitchen gut in Pilsen last spring and the sub called me two days before the deadline to renegotiate his schedule, first time that ever happened. You won't recover the $2,100 from this guy regardless, but the next contract needs that number in it or the date means nothing.