My Scottdale duplex has been sitting with a half-finished bathroom for eleven weeks and I still don't know if that's on me or the GC
Hired him in March, $18,400 scope, demo and rough plumbing went fast and then nothing. He says the tile sub is backed up. I called two tile subs myself last week and both said they could start within ten days if I brought them in direct. So now I don't know if he actually has a sub lined up or if he's just managing my expectations while he works somewhere else. Contract says completion by end of April and we're well past that. I haven't withheld the third draw yet because I wasn't sure if that would just make him walk, and the rough plumbing that's already in the walls is his work, so I'd rather not start over with someone who didn't do it. Curious whether anyone has actually replaced a GC mid-job on a bathroom scope this small and what that handoff looked like practically, because everything I keep reading is about big gut rehabs, not a $6k tile and vanity finish.