Designer moved the primary bath after the slabs were cut, seven weeks gone
Project is a 1990s builder-luxury house in a strong high-end submarket, 4,600 square feet, target 4.1M. Purchase 2.44M, reno budgeted at 720k, currently trending 785k before this. Hard money at 2.1M, 8 months left on the term, extension is a point plus a rate bump and I need to confirm the exact terms in writing again because I'm working off a phone call.
My equity partner brought in a designer with genuine high-end credentials. She looked at the primary bath at week nine, after the two slabs were cut for the double vanity and the shower bench, and said the layout reads like a 2005 remodel. She wants the tub moved off the window wall, the shower expanded into the closet, and a wet room. Plumbing rough is in. Framing is in. The slabs are cut for a layout that no longer exists.
Change order came back at 47k and seven weeks. Seven weeks is my entire float. My monthly carry is roughly 22,900 all in, so the schedule alone is about 37k, meaning the real number is 84k and I'm at 869k on a 720k budget.
Option two is I hold the original layout and eat the designer's opinion. The slabs stay usable, no plumbing rework, I keep the float and list in the spring window instead of after Labor Day.
What I can't get anyone to answer with a number is whether the wet room actually moves the price. My agent says "buyers at 4M expect it" which is not a number. My partner says missing spring is worse than a dated bath. I have to sign or kill the CO by Thursday.