Does anybody actually model a construction contingency as a live budget line or just set it and forget it
I had 8 percent baked into the LTC on a 14 unit project in Stark County and watched the GC pull from it twice before framing was done. By month four it was gone and we were having a different conversation. The number I see most often is 5 to 10 percent depending on who you ask, but what I have never seen clearly spelled out is whether that contingency is meant to absorb owner scope changes, contractor error, or pure market volatility on materials. Those are three different risk sources and pooling them into one line seems like it sets you up to feel fine until you are not. On the Fresno deal I was involved with, the contingency sat untouched for seven months and then got consumed in about six weeks when subcontractor pricing on electrical came in 22 percent over the original sub bid. Nobody had flagged electrical as the exposure. The contingency did its job technically but it also masked the fact that the original sub bid was soft. I am curious whether people actually reforecast that line monthly against known risks, or whether it just sits there as a comfort number until a draw meeting forces the issue.