My construction loan closed at 65 percent LTC and I thought I had it figured out
Nine months in, the draw schedule is running about three weeks behind the actual work, and the lender's inspector only releases on what's fully complete, not what's substantially complete. That gap sounds administrative until you're carrying a $4,200 per week interest drag out of pocket because the framing crew finished floor three before the mechanical rough-in on floor two got signed off. I have 34 units going up outside of Cedar City and I am funding about $11,000 a month from reserves that I budgeted for contingency. The contingency is fine, the reserves are being depleted for the wrong reason. What nobody told me before close was that "construction lender" and "draw administrator" are not the same job, and my lender does not see sequencing as their problem.