Only 16 of 48 MW are energized and the promote clock starts anyway
Sponsor wants $6M from us by the 19th and I'm stuck on the phasing.
Single asset vehicle, 48 MW of contracted critical load in an emerging Sun Belt market off the I-20 corridor. Total capitalization $456M, so about $9.5M per MW. One investment grade cloud tenant, 15-year lease, 2.5% annual escalators, rent quoted at $105 per kW per month on energized capacity only, two 5-year renewals at market with a floor.
The phasing is what I keep rereading. 16 MW energized at closing. The remaining 32 MW arrives in two 16 MW blocks tied to a utility substation upgrade, currently scheduled at month 14 and month 26. Rent commences per phase on energization, not on delivery of the hall. Sponsor's base case gets to roughly $52M of stabilized NOI against $456M, call it 11.4% on cost, exit at 6.25% in year 11.
What I've actually read: a will-serve letter with an in-service estimate and a page of conditions I don't fully follow, an EPC contract with liquidated damages capped at 5% of contract value, and a lease with an outside delivery date the tenant can walk against if phase two slips past month 32.
Where I can't get comfortable. If the substation slips a year, that delayed 32 MW is about $40M of annual rent arriving late, and the promote measures IRR from first dollar in, so the sponsor's clock runs whether the power shows up or not. Separately I don't believe a 6.25% exit on a year-11 air-cooled hall without doing more work on what liquid cooling retrofits cost.
The alternative is a smaller slice of a diversified operator platform, lower fee load, much less single-phase risk. It's one or the other by the 19th.