Took the house back at month 9 and still came out around 12 percent
I usually borrow this money, not lend it. Sold a flip last spring, had $215k sitting between deals, and a wholesaler I've worked with introduced a borrower doing a full renovation on a 1950s three bedroom in an established suburb. I decided I'd rather earn 11 and 2 on someone else's project for a year than rush into a mediocre one of my own.
Structure: $215,000 total, $170k funded at acquisition, $45k rehab holdback in four draws. Purchase price $190k, borrower brought $27k plus closing costs. Rehab budget $62k, ARV $355k. First position deed of trust, lender's title policy, named on the hazard policy, 12 month interest only at 11 percent, 2 points, default rate spelled out, borrower paid all closing costs. 61 percent of ARV, and 89 percent of as-is purchase price, which is the number I actually watched.
What happened: draws one and two went normally, inspected each time. Draw three came in month 5 with the kitchen half done and the inspector's percentage complete well below what the borrower claimed. I funded part of it and held the rest. He stopped paying in month 7. Turned out he had two other projects and this was the one he'd decided to let go.
Month 9 we agreed to a deed in lieu. My attorney handled it and told me exactly which risks I was accepting by taking title that way rather than foreclosing, including the liens I'd be taking subject to. That's a conversation you have with counsel in your own state, not a forum decision. I got a title update first and found $4,100 of unpaid taxes and one contractor claim for $9,400 that I negotiated to $6,200.
Then I did the thing most lenders can't, which is finish it. About $22k of work with my own crew over seven weeks. Listed at $349k, sold at $338k, closed month 13.
Rough accounting on the $215k: interest actually collected through month 6 was about $11,800, points $4,300, and the sale returned my principal plus enough to cover the taxes, the lien settlement, the $22k of completion cost, carrying costs of roughly $7,600, and about $9,100 on top. Call it $25,200 total on $215k over thirteen months, so a bit under 11 percent annualized, and I'm not counting my crew's time at anything but cost.
What nearly broke it: the unfunded $12k of draw three. If I'd released it on his word the way I would have a year earlier, that money would have gone to one of his other projects and I'd have been $12k deeper into a house that was further from done.
What I'd keep: the holdback with real inspections, watching loan to as-is rather than loan to ARV, and only lending on work I could finish myself.