Renovation ran 340k over, and the capital call hit nine people who thought it was fine
Numbers first so nobody has to ask. 14 unit brick walk-up, pre-1940, second tier midwest market, bought for 1.02m with a 700k bridge and 1.35m of LP equity from nine investors. Renovation budget 720k with 90k of contingency inside it. I was in for 5 percent of the equity with a 20 percent promote over an 8 percent pref. Full gut on ten units, cosmetic on four, 11 month schedule.
Renovation closed out at 1.06m. Fourteen months, not eleven.
The cost driver was electrical. We opened three units in month two, found knob and tube behind plaster, and priced the rest off those three. When we got into units four through ten the wiring runs were different in the rear stack and the service could not carry the load, so we ended up with a new service, a new panel per unit, and a fire alarm upgrade the building department wanted once the permit scope crossed into a full gut on more than half the units. That trigger is a local code question and it varies by city, which I did not check before I priced anything. Contingency was gone in month four. Bridge extension cost me two points and five extra months of carry.
The part that actually cost me the business is the reporting. My quarterly updates through the middle of the job said we were on schedule and tracking to budget, because I was reading percent complete off the schedule instead of cost to complete off the remaining scope. Both quarterlies were honest and both were wrong. Month eleven I sent nine people an email asking for 340k pro rata, and it was the first bad news any of them had ever had from me.
Four of nine funded, 155k. To close the gap I took 340k of rescue capital at a 12 percent current pay sitting ahead of the entire LP stack with 25 percent of the residual. My operating agreement let me admit that capital without an LP vote. The original 1.35m now sits behind money that showed up last. The deal will most likely give people their principal back and a thin number on top. My promote is worth nothing, which I can live with. Three of the nine will not answer me, and that is the real bill.
What I would do differently. Report cost to complete every month against the remaining contingency, in dollars, with the contingency balance printed on the page. Send the email the week the contingency hits zero, not the quarter I need money. Have the capital call mechanics and the exact dilution math written into the docs and walked through out loud before anyone wires, so a call is a known feature rather than an ambush. And line up a backstop before I need it, because rescue capital priced at 12 percent and a quarter of the upside is what you pay when the only alternative is stopping the job.