Preferred equity came in as rescue capital and the GP lost the promote two years before the sale
A manufactured housing community deal worth studying: a 180-pad community underwritten at 92 percent occupancy, with a value-add plan built around infilling 22 vacant pads over 18 months. The sponsor raised $3.2M in LP equity and placed $4.8M in senior debt, with a preferred return of 8 percent and a 70/30 split above a 1.6x equity multiple. Eighteen months in, pad fill had reached 9 of the 22 targeted, utility cap installation was six months behind schedule, and the debt service coverage had slipped to 1.08 against a 1.25 covenant. The lender issued a notice of potential default. The sponsor had two options: inject additional GP capital, which the principals could not do at that scale, or bring in a rescue equity partner. They chose the rescue. The preferred equity came in at $900,000, senior to LP equity in the waterfall, at a 12 percent preferred return, with a conversion right that effectively subordinated the common promote until the preferred equity was fully returned with its coupon. When the asset sold 26 months later at a number that covered the senior debt, the preferred equity, and the LP preferred return, there was $180,000 left above the LP pref threshold. The promote split on $180,000 gave the GP $54,000. The original promote projection at underwriting was $410,000. The mechanism that produced that outcome was not the sale price, which came in close to the original projection. It was the preferred equity sitting ahead of the promote in the waterfall, and the GP signed that term sheet under duress without modeling what the promote looked like at three different exit prices. The assumption doing the most work in the original underwrite was the 18-month pad fill timeline, and that timeline had no permit history or contractor commitment behind it, only a market absorption estimate. If the pad fill had tracked the schedule, the lender covenant would not have been breached and the rescue capital would never have entered. What was the basis for the pad fill timeline in your underwrite, a signed installer agreement or a comparable absorption study from a nearby community?