Lakewood ranch is finally making money and it took three extra months of carrying costs to get here
Closed on this one in late January, 1958 ranch, 1,340 square feet, Lakewood. Purchase was $312,000, hard money at 11.5%, and my original rehab budget was $94,000 with a 90-day project timeline. I had the place listed in my head by late April. It is now the first week of May and I am still not done, the GC just handed me a revised schedule that puts substantial completion at May 28th, which means I am looking at a June listing if I am lucky.
The carrying costs on hard money are not theoretical pain. At $312,000 financed, I am paying roughly $3,000 a month in interest alone. Property taxes in Jefferson County run me another $340 a month prorated. I carry a builder's risk policy that adds $210 a month. Utilities I cannot kill because the GC needs power and the pipes need to stay pressurized, another $180 a month average. So call it $3,730 a month in pure holding cost on a project I thought would run three months and has now run four and a half heading toward five.
The wall situation I mentioned before added six weeks to the timeline, not because the beam itself took six weeks but because the structural engineer took three weeks to get out there, then the permit amendment took another two, and then my framing crew had moved to another job in the gap so I lost a week on scheduling. You do not lose six weeks on a beam. You lose six weeks on the chain of people and approvals attached to the beam.
That extra two months I did not plan for is $7,460 in holding costs I did not underwrite. My contingency was $9,400, which is 10% of rehab, so I am not dead, but the contingency is basically gone to carrying costs and the structural work and I have zero cushion left going into the final punch list. If the HVAC inspection kicks back anything or the county wants a re-inspection on the electrical I am dipping into projected profit.
ARV is still holding around $485,000 based on two comps that closed in March, though one of those was a newer build and I am not sure the appraiser will give me full credit on finishes. If I hit $480,000 net of 6% commissions and closing I am at $451,200. Subtract $312,000 purchase, $94,000 rehab, $14,000 in overruns, and the $3,730 times five months of holding and I am at roughly $12,550 in profit before my capital costs outside the hard money loan. That is not a loss. I will take it. But I underwrote this deal at closer to $40,000 and the gap is almost entirely timeline.